Audit Workflow
The chronological phase chain of the May 2026 frontend audit — what shipped, where the project sits today, and what's left before R1/R2/R3 certify.
Phases Total10
Done6
TodayStakeholder Read-out
Pinned SHA49d4c7d
Phase 7 of 10
📍 TodayStakeholder Read-out
Live walk-through of the report with stakeholders. Lock ownership, lock dates, lock blocker counts. After this point edits are change-control.
Start:
2026-05-22End:
2026-05-22Outputs
Locked tracker + final verdict snapshot
Verdict Snapshot
R1→NOT READY19 +3
R2→NOT READY4
R3→NOT READY22 +2
Total findings indexed122
How to read this timeline
✓Done
Phase has shipped its output; numbers in the verdict snapshot are frozen against this work.
Today
Where the project sits right now (2026-05-22).
Upcoming
Scheduled work that depends on the prior phase completing. Dates fix at the read-out.
★Target
The certification milestone — the moment R1/R2/R3 flip from NOT READY to READY.